KAJIAN ANOMALI POLE MOUNTED RECLOSER MENGGUNAKAN METODE STAR – PROTECTION & COORDINATION PADA PENYULANG CILOGRANG GARDU INDUK BAYAH PT. PLN (PERSERO) UNIT PELAKSANA PELAYANAN PELANGGAN BANTEN SELATAN

FAHDULHAQ, YANDA and Ispranyoto, Edy (2022) KAJIAN ANOMALI POLE MOUNTED RECLOSER MENGGUNAKAN METODE STAR – PROTECTION & COORDINATION PADA PENYULANG CILOGRANG GARDU INDUK BAYAH PT. PLN (PERSERO) UNIT PELAKSANA PELAYANAN PELANGGAN BANTEN SELATAN. Diploma thesis, ITPLN.

[thumbnail of PROYEK AKHIR_YANDA FAHDULHAQ_201971065_YANDA FAHDULHAQ.pdf] Text
PROYEK AKHIR_YANDA FAHDULHAQ_201971065_YANDA FAHDULHAQ.pdf
Restricted to Registered users only

Download (3MB)

Abstract

Pada penyulang Cilograng sebelumnya pernah terjadi gangguan arus pada sistem jaringan SUTM yang mengakibatkan padamnya saluran listrik pada penyulang Cilograng. Didapatkan laporan bahwa pole mounted recloser (PMR) Jawatie trip dan setelah ditelusuri bahwa gangguan arus tersebut disebabkan karena adanya pohon yang roboh pada SUTM dekat dengan gardu distribusi CLB yang mana masih dalam daerah kerja PMR Rinjani. Penelitian ini bertujuan mengetahui koordinasi proteksi. Metode yang digunakan pada penelitian ini yaitu Star–Protection & Coordination yaitu dengan mengumpulkan data single line diagram penyulang, data Gardu Induk serta data setting proteksi ketika terjadi anomali dan sesudah diselesaikan anomali di lapangan untuk disimulasikan. Pertama merangkainya kemudian memberikan perintah fault insertion untuk memberikan gangguan setelah itu perintah Sequence viewer untuk mengetahui waktu kerja relay. Terakhir memberi perintah create star view untuk mengetahui grafik kerja relay pada penyulang cilograng. Kesimpulannya bahwa besaran arus hubung singkat pada metode ini mendekati dengan hasil perhitungan yang membuatnya tidak sama adalah karena pada metode ini banyak sekali faktor yang membuat nilainya dapat. Settingan relay yang didapat itu dengan memberikan gap. Berdasarkan hasil waktu kerja relay yang telah dilakukan dapat terlihat bahwa menunjukkan proteksi berkoordinasi dengan baik karena relay rinjani yang bekerja terlebih dahulu.

In the previous Cilograng feeder, there had been a current disturbance in the SUTM network system which resulted in blackouts in the Cilograng feeder. It was reported that the pole mounted recloser (PMR) of Jawatie had tripped and after being investigated that the current disturbance was caused by a fallen tree at SUTM close to the CLB distribution substation which is still in the work area of PMR Rinjani. This study aims to determine the coordination of protection. The method used in this study is Star – Protection & Coordination, namely by collecting data on single line diagrams of feeders, data on substations and data on protection settings when an anomaly occurs and after anomaly is resolved in the field to be simulated. First, assemble it and then give the fault insertion command to provide interference, then the Sequence viewer command to find out the working time of the relay. Finally, give the command create star view to find out the graph of relay work on the cilograng feeder. The conclusion is that the amount of short-circuit current in this method is close to the calculation results which makes it not the same because in this method there are many factors that make the value possible. The relay setting obtained is by providing a gap. Based on the results of the working time of the relay that has been done, it can be seen that it shows that the protection is coordinated well because the Rinjani relay works first.

Item Type: Thesis (Diploma)
Uncontrolled Keywords: Anomali, Proteksi, Recloser, ETAP Anomaly, Protection, Recloser, ETAP
Subjects: Skripsi
Bidang Keilmuan > Teknik Tenaga Listrik
Divisions: Vokasi > D3 Teknologi Listrik
Depositing User: Sudarman
Date Deposited: 22 Apr 2026 06:29
Last Modified: 22 Apr 2026 06:29
URI: https://repository.itpln.ac.id/id/eprint/6476

Actions (login required)

View Item
View Item