Pratiwi, Ella Ayu and Sepriyanna, Irma (2025) ANALISIS PRODUKTIVITAS TENAGA KERJA DAN ALAT BERAT TOWER CRANE PADA PEKERJAAN KOLOM DI PROYEK PEMBANGUNAN RUMAH SUSUN NUANSA TOWER B CILANGKAP. Diploma thesis, ITPLN.
![[thumbnail of SKIRIPSI_202021004_ELLA AYU PRATIWI.pdf]](https://repository.itpln.ac.id/style/images/fileicons/text.png)
SKIRIPSI_202021004_ELLA AYU PRATIWI.pdf
Restricted to Registered users only
Download (2MB)
Abstract
Penelitian ini bertujuan untuk menganalisis produktivitas tenaga kerja dan alat berat tower crane pada proyek pembangunan Rumah Susun Nuansa Tower B Cilangkap dengan mengukur siklus waktu pekerjaan pembesian, bekisting, dan pengecoran kolom. Sangat penting untuk memastikan keberhasilan proyek salah satu caranya dengan menganalisis produktivitas tenaga kerja dan alat berat yang digunakan. Data diperoleh melalui pengamatan langsung di lapangan dan pengumpulan informasi serta perhitungan terkait volume pekerjaan serta siklus waktu. Hasil analisis menunjukkan bahwa volume pekerjaan pembesian per kolom sebesar 606,50 kg, volume bekisting lantai 18 sebesar 7,2 m² dan lantai 19 sebesar 6,6 m², serta volume pengecoran lantai 18 dan 19 masing masing sebesar 1,05 m³ dan 0,9 m³. Waktu siklus pekerjaan pembesian dan pekerjaan bekisting adalah 7 jam/hari, sementara waktu siklus tower crane pada pekerjaan pengecoran pada lantai 18 sebesar 1 jam 6 menit dan lantai 19 adalah 1 jam 8 menit. Sedangkan nilai produktivitas tenaga kerja untuk pekerjaan pembesian mencapai rata-rata 308,31 kg/OH, lebih tinggi dari standar SNI 7394:2008 sebesar 215 kg/OH. Sebaliknya, produktivitas pekerjaan bekisting di lapangan hanya mencapai 3,75 m²/OH, lebih rendah dibandingkan standar SNI sebesar 4,24 m²/OH. Untuk pekerjaan pengecoran, penggunaan alat berat berupa tower crane menunjukkan produktivitas sebesar 10,44 m³/jam di lantai 18 dan 7,92 m³/jam di lantai 19. Temuan ini mengindikasikan bahwa pelaksanaan pekerjaan pembesian cukup efisien, sementara pekerjaan bekisting masih memerlukan peningkatan. Performa alat berat juga menunjukkan efisiensi yang bervariasi tergantung lantai pekerjaan.
This study aims to analyze the productivity of labor and tower crane equipment in the Nuansa Tower B Cilangkap flat construction project by measuring the work cycle of reinforcement, formwork, and concrete casting for columns. Ensuring the success of a construction project requires, among other things, an analysis of labor and equipment productivity. Data were obtained through direct field observation and collection of information and calculations related to work volume and cycle times. The analysis results show that the volume of reinforcement work per column is 606.50 kg, formwork volume on the 18th floor is 7.2 m², and on the 19th floor is 6.6 m². The casting volume for columns on the 18th and 19th floors is 1.05 m³ and 0.9 m³, respectively. The work cycle duration for reinforcement and formwork is 7 hours per day, while the tower crane cycle time during casting is 1 hour 6 minutes on the 18th floor and 1 hour 8 minutes on the 19th floor. Labor productivity for reinforcement work averages 308.31 kg/worker-hour (OH), which is higher than the standard stated in SNI 7394:2008, which is 215 kg/OH. In contrast, productivity for formwork is only 3.75 m²/OH, lower than the SNI standard of 4.24 m²/OH. For casting work, the productivity of the tower crane reached 10.44 m³/hour on the 18th floor and 7.92 m³/hour on the 19th floor. These findings indicate that reinforcement work is relatively efficient, whereas formwork activities require improvement. Equipment performance, particularly of the tower crane, also showed varying levels of efficiency depending on the floor level.
Item Type: | Thesis (Diploma) |
---|---|
Uncontrolled Keywords: | Produktivitas, Tenaga Kerja, Tower Crane, Kolom, SNI 7394:2008 Productivity, Labor, Tower Crane, Column, SNI 7394:2008. |
Subjects: | Bidang Keilmuan > Teknik Sipil Skripsi |
Divisions: | Fakultas Teknologi Infrastruktur dan Kewilayahan > S1 Teknik SIpil |
Depositing User: | Sudarman |