Putra, I Gusti Ngurah Agung Sutrisna Dwi and Widyastuti, Christine (2025) INVESTIGASI GANGGUAN RECLOSE SUKSES SUTT 150 kV GIANYAR - AMLAPURA 1,2 DAN PERBAIKAN DENGAN METODE PEMASANGAN GROUNDING LANGSUNG DI TOWER NO 66 DAN 67 PLN UPT BALI. Diploma thesis, Institut Teknologi PLN.
SKRIPSI 202211923 I GUSTI NGURAH AGUNG SUTRISNA DWI PUTRA.pdf
Restricted to Registered users only
Download (5MB)
Abstract
PT PLN UPT Bali sebagai pengelola aset jaringan transmisi 150 kV di Pulau Bali yang salah satu mempunyai target setiap tahunnya adalah untuk menurunkan jumlah kali dan lama waktu gangguan yang terjadi di Saluran Udara Tegangan Tingggi (SUTT) 150 kV supaya penyaluran energi listrik kepada pelanggan menjadi handal. Berdasarkan data gangguan yang pernah terjadi dari tahun 2019 sampai tahun 2024, tercatat di tahun 2019 dan 2022 gangguan yang terjadi di SUTT 150 kV akibat petir masing-masing sebanyak 5 kali. Penelitian ini dilakukan untuk memperbaiki nilai tahanan sistem pentanahan pada kaki tower jaringan SUTT 150 kV Gianyar - Amlapura 1,2. Hasil pengukuran nilai tahanan pentanahan pada tahun 2023 pada kaki tower No 67 nilai terbesarnya adalah 30,80 ohm. Tahanan pentanahan kaki tower transmisi ditetapkan kurang dari 10 ohm. Tahanan pentanahan yang melebihi nilai ini tidak menjamin keamanan proteksi petir, back flashover sangat berpeluang terjadi pada keadaan ini. Bentuk konfigurasi jaringan transmisi SUTT 150 kV Gianyar - Amlapura 1,2 berupa radial yang menyalurkan energi listrik dari GI Gianyar menuju GI Amlapura. Oleh karena itu, diperlukan metode yang efektif dan efisien untuk mengantisipasi permasalahan diatas supaya tidak terulang kembali yaitu dengan pemasangan grounding langsung. Hasil dari pengukuran nilai tahanan pentanahan setelah pemasangan grounding langsung di tower 66 dan 67 berturut-turut yaitu 0,35 ohm dan 4,64 ohm.
PT PLN UPT Bali as asset manager of the 150 kV transmission network on the island of Bali, one of its annual targets is to reduce the number of times and duration of disruptions that occur on the 150 kV High Voltage Overhead Line (SUTT) so that the distribution of electrical energy to customers becomes reliable. Based on data on disturbances that have occurred from 2019 to 2024, it was recorded that in 2019 and 2022 disturbances occurred at the 150 kV SUTT due to lightning 5 times each. This research was carried out to improve the resistance value of the grounding system at the foot of the SUTT 150 kV Gianyar - Amlapura 1,2 network tower. The results of measuring the ground resistance value in 2023 at the foot of tower No. 67, the largest value is 30.80 ohms. The grounding resistance of the transmission tower legs is determined to be less than 10 ohms. Grounding resistance that exceeds this value does not guarantee the safety of lightning protection, back flashover is very likely to occur in this situation. The configuration of the 150 kV Gianyar - Amlapura SUTT transmission network 1,2 is in the form of a radial that distributes electrical energy from the GI Gianyar to the GI Amlapura. Therefore, an effective and efficient method is needed to anticipate the above problems so that they do not happen again, namely by installing direct grounding. The results of measuring the grounding resistance value after installing direct grounding on towers 66 and 67 were respectively 0.35 ohms and 4.64 ohms.
| Item Type: | Thesis (Diploma) |
|---|---|
| Uncontrolled Keywords: | SUTT 150 kV, Gangguan akibat petir, Nilai tahanan pentanahan, Pemasangan grounding langsung SUTT 150 kV, Disturbances due to lightning, Value of grounding resistance, Installation of direct grounding. |
| Subjects: | Bidang Keilmuan > Electrical Engineering Skripsi Bidang Keilmuan > Teknik Elektro |