Badi, Muhammad Razak Al Munawan and Sepriyanna, Irma (2024) ANALISIS FAKTOR PENYEBAB KETERLAMBATAN PEKERJAAN BORE PILE DENGAN MENGGUNAKAN METODE FTA (FAULT TREE ANALYSIS) PADA PROYEK PEMBANGUNAN GEDUNG BSI TOWER JAKARTA PUSAT. Diploma thesis, ITPLN.
![[thumbnail of SKRIPSI MUH.RAZAK_I-V_202021073.pdf]](https://repository.itpln.ac.id/style/images/fileicons/text.png)
SKRIPSI MUH.RAZAK_I-V_202021073.pdf
Restricted to Repository staff only
Download (2MB)
Abstract
Proyek pembangunan gedung BSI Tower jakarta pusat, terutama pada pekerjaan pondasi bore pile tidak sesuai dengan jadwal yang direncanakan pada penjadwalan awal. Dimana pada jadwal awal rencana pekerjaan bore pile dimulai pada tanggal 26 Oktober 2023 dan berakhir di 14 januari 2024 dengan jumlah titik pekerjaan sebanyak 342 titik namun pada aktualnya pekerjaan bore pile selesai pada tanggal 26 Maret 2024 oleh karena itu penelitian ini menitik beratkan pada permasalahan-permasalahan yang menjadi faktor faktor penyebab keterlambatan pekerjaannya. Pengumpulan data pada penelitian ini menggunakan teknik observasi, wawancara dan kuesioner. Sampel yang digunakan dalam penelitian ini diambil dengan menggunakan teknik purposive sampling dengan jumlah sebanyak 15 orang. Data yang terkumpul sebelumnya diolah terlebih dahulu kemudian di analisis dengan menggunakan metode FTA (Fault Tree Analysis) yang dapat digunakan untuk menganalisa suatu keterlambatan sebuah pekerjaan serta dapat mengetahui besic event dan top even dari penyebab keterlambatan pekerjaan. Dari data yang telah di dapat kemudian analisa MOCUS yang merupakan salah satuh metode dari aljabar boolean baik dari segi pendekatan top down dan bottom up pada metode FTA bahwa faktor kontraktrolah yang memiliki kombinasi basic event paling banyak yaitu sebanyak 16 kombinasi sedangakan faktor lingkungan hanya menghasilkan 9 kombinasi dengan tingkat nilai probabilitas yang berbeda-beda.
The BSI Tower building construction project in Central Jakarta, especially the bore pile foundation work, is not in accordance with the schedule planned in the initial scheduling. Where in the initial schedule the bore pile work was planned to start on 26 October 2023, and end on 14 January 2024, with a total of 342 work points, but the bore pile work was completed on March 26, 2024, therefore this research focuses on the problems which are the factors causing delays in work. Data collection in this research used observation, interview and questionnaire techniques. The sample used in this research was taken using a purposive sampling technique with a total of 15 people. The previously collected data is processed first and then analyzed using the FTA (Fault Tree Analysis) method which can be used to analyze delays in work and can determine the main events and top events of the causes of work delays. From the data that has been obtained, MOCUS analysis, which is a method of Boolean algebra, both in terms of top down and bottom-up approaches in the FTA method, shows that the contract factor has the most basic event combinations, namely 16 combinations, while the environmental factors only produce 9 combinations. with different levels of probability values.
Item Type: | Thesis (Diploma) |
---|---|
Uncontrolled Keywords: | Fault Tree Analysis (FTA), Keterlambatan, Bore Pile, Aljabar Boolean Fault Tree Analysis (FTA), Delay, Bore Pile, Aljabar Boolean |
Subjects: | Bidang Keilmuan > Teknik Sipil Skripsi |
Divisions: | Fakultas Teknologi Infrastruktur dan Kewilayahan > S1 Teknik SIpil |
Depositing User: | Sudarman |
Date Deposited: | 28 Aug 2025 03:24 |
Last Modified: | 28 Aug 2025 03:24 |
URI: | https://repository.itpln.ac.id/id/eprint/300 |