Simanjuntak, Ernesto Einrich and Rahayu, Sofitri (2024) ANALISIS PERBAIKAN SUSUT PADA JARINGAN TEGANGAN RENDAH TERHADAP SUSUT TEKNIS DENGAN SIMULASI ETAP 19.0.1 DI PT PLN (Persero) UNITLAYANAN WARUJAYENG. Diploma thesis, ITPLN.
SKRIPSI 202211535 ERNESTO EINRICH SIMANJUNTAK.pdf
Restricted to Registered users only
Download (11MB)
Abstract
Rugi daya pada suatu sistem tenaga listrik tak dapat dihindari. Oleh karena itu PT. PLN (Persero) ULP Warujaueng menetapkan target bahwa rugi daya pada suatu sistem di Warujayeng hendaknya tidak lebih dari 1%. Susut merupakan hal perlu diperhatikan, karena dapat mempengaruhi efisiensi pengiriman energi dari Pembangkit hingga ke konsumen. Biaya susut sendiri akan di beban kan kepada pelanggan untuk biaya operasional. Tentu hal tersebut merupakan isu yang perlu perhatian untuk meminimalisasi susut yang terjadi. Untuk melihat sejauh mana rugi daya akibat sistem distribusi tenaga listrik hendaknya perlu dilakukan kajian lebih lanjut. Penelitian ini berfokus pada salah satu penyulang yaitu penyulang Kalianyar. Penelitian ini menggunakan data sekunder yang diperoleh dari ULP Warujayeng berdasarkan data pengukuran pada Tahun 2023 mengalami susut daya sebesar 10.51% dengan target yang ditentukan yaitu 8.78%. Berdasarkan hasil analisis dan simulasi perbaikan pada ETAP 19.0.1, pecah beban merupakan cara aman untuk menurunkan susut adalah optimisasi konfigurasi transformator, dan peningkatan efisiensi operasional melalui pemantauan yang lebih baik terhadap beban dan konsumsi daya. Seperti yang di ketahui susut dipengaruhi banyak hal, seperti panjang kabel, jenis kabel, luas penampang kabel juga.
Power loss in a power system cannot be avoided. Therefore, PT PLN (Persero) ULP Warujaueng sets a target that the power loss in a system in Warujayeng should be no more than 1%. Power loss is something that needs to be considered, because it can affect the efficiency of energy delivery from the Power Plant to consumers. The cost of shrinkage itself will be charged to customers for operational costs. Of course this is an issue that needs attention to minimise the shrinkage that occurs. To see the extent of power loss due to the power distribution system, further studies should be conducted. This research focuses on one of the power distribution system, namely Kalianyar power distribution system. This research uses secondary data obtained from ULP Warujayeng based on measurement data in 2023 experiencing power losses of 10.51% with a specified target of 8.78%. Based on the results of analysis and simulation of improvements in ETAP 19.0.1, load shedding is a safe way to reduce shrinkage is optimisation of transformer configurations, and increased operational efficiency through better monitoring of loads and power consumption. As it is known that shrinkage is influenced by many things, such as cable length, cable type, cable cross-sectional area as well.
| Item Type: | Thesis (Diploma) |
|---|---|
| Uncontrolled Keywords: | Susut, pecah beban, overload. Powerlosses, load shedding, overload. |
| Subjects: | Skripsi Bidang Keilmuan > Teknik Elektro |
| Divisions: | Fakultas Ketenagalistrikan dan Energi Terbarukan > S1 Teknik Elektro |
| Depositing User: | Sudarman |
| Date Deposited: | 06 Nov 2025 03:40 |
| Last Modified: | 06 Nov 2025 03:40 |
| URI: | https://repository.itpln.ac.id/id/eprint/3480 |