PENGARUH PLUGGING TERHADAP EFEKTIVITAS CONDENSER UNIT 2 PLTU 4 BANGKA BELITUNG

SURYADANI, FAWZI AKBAR and Prabowo, Eri (2023) PENGARUH PLUGGING TERHADAP EFEKTIVITAS CONDENSER UNIT 2 PLTU 4 BANGKA BELITUNG. Diploma thesis, ITPLN.

[thumbnail of SKRIPSI_Fawzi Akbar S_202012143.pdf] Text
SKRIPSI_Fawzi Akbar S_202012143.pdf
Restricted to Repository staff only

Download (28MB)

Abstract

Condenser merupakan salah satu alat bantu yang mendukung kehandalan operasi PLTU 4 Bangka Belitung. Condenser berfungsi mengkondensasikan uap keluaran dari turbin
dan merubahnya menjadi air kondensat dengan metode transfer panas dengan media pendinginnya berupa air laut. Struktur condenser di PLTU 4 Bangka Belitung bertipe shell and tube heat exchanger, dimana uap keluaran turbin masuk pada bagian shell dengan nilai kevakuman tertentu sedangkan pada bagian tube diisi air pendingin berupa air laut. Kebocoran pada tube condenser sering terjadi mengingat material tube
langsung bersinggungan dengan air laut dengan kadar garam dan konduktiviti yang tinggi. Jika terjadi kebocoran pada tube, hal ini akan menyebabkan air kondensat terkontaminasi oleh garam dari air laut sehingga akan menyebabkan kerusakan pada komponen yang dilewati oleh air kondensat tersebut. Oleh karena itu, apabila dijumpai terjadi kebocoran tube condenser maka harus segera dilakukan plugging pada tube
condenser. Dengan plugging pada condenser ini maka akan mengurangi nilai efektivitas condenser. Setelah dilakukan perhitungan efektivitas condenser pada kondisi sebelum dan sesudah pluigging , diperoleh hasil bawah pada operasi beban yang bervariasi pada 15.5 MW 14.5 MW dan 13.7 MW , plugging sejumlah 9.74% atau sejumlah 342 tube dari total 3520 tube akan menyebabkan penurunan efektivitas condenser masing masing sebesar ± 5 %, 2% dan 4%.

Condenser is a supporting component of the operation of PLTU 4 Bangka Belitung. Condenser condense and convert the exhaust steam from steam turbine to the condensate water using heat transfer methode used sea water as cooling medium. Condenser in PLTU 4 Bangka Belitung is shell and tube heat exchanger, whereas the exhaust steam from turbine enter the condenser shell by certain vacuum, while the condenser tube is filled by cooling water from the ocean. The leakage of tube occur considering the tube is in direct contact with sea water with high conductivity. If there is a leakage, this will cause the condensate water to be contaminated by salt from the sea water and will cause damage to the components the condensate water passes through. Therefore, if a condenser tube leak is found, plugging in the condenser tube must be done immediately. Plugging methode will decrese the effectiveness of the condenser. After calculating the effectiveness of the condenser in the conditions before and after plugging at the variation load operation of 15.5 MW, 14.5 MW and 13.7 MW , plugging of 9.74% of a total of 3520 tubes decrease the condensor’s effectivity of ± 5%, 2% and 4% each.

Item Type: Thesis (Diploma)
Uncontrolled Keywords: condenser, plugging, efektivitas, shell and tube condenser, plugging, efektivitas, shell and tube
Subjects: Skripsi
Bidang Keilmuan > Teknik Mesin
Divisions: Fakultas Teknologi dan Bisnis Energi > S1 Teknik Mesin
Depositing User: Nurul Hidayati
Date Deposited: 31 Aug 2025 18:44
Last Modified: 31 Aug 2025 18:44
URI: https://repository.itpln.ac.id/id/eprint/387

Actions (login required)

View Item
View Item