Irfan, Muhamad Nurul and Hafidz, Mohammad (2017) ANALISIS KINERJA SISTEM KONTROL PEMBANGKIT LISTRIKTENAGA MIKRO HIDRO MELONG SUBANG, JAWA BARAT. Diploma thesis, ITPLN.
skripsi irfan 201311294.pdf
Restricted to Registered users only
Download (644kB)
Abstract
Pembangkit Listrik Tenaga Mikro Hidro ialah Pembangkit Listrik Tenaga Air yang berskala kecil dengan batasan kapasitas antara 5 KW – 200 KW per unit. Komponen utama dari PLTMH Melong yaitu Bangunan Sipil, Komponen Mekanikal dan Komponen elektrikal yang terdiri dari generator dan sistemkontrol, sistem kontrol pada PLTMH Melong ada dua bagian yang harus dijaga konstan agar PLTMH selalu beroperasi yaitu tegangan dan frekuensi. Pengontrolan tegangan dapat diatur dengan AVR (Automatic Voltage Regulation) untuk jenis generator sinkron type STAMFORD, UCI 274 E. Jika untuk pengaturan frekuensi dapat diatur dengan Guide Vane Electro Governor Hydraulic. Dari pengaturan sistem kontrol PLTMH, Daya Aktif (P) yang dhasilkan pada output generator perlu adanya Daya Reaktif (Q), Daya Semu (S) yang mempengaruhi kinerja sistem kontrol serta dibandingkan dengan program ETAP 12.6.0.
Micro Hydro power plant is a power plant water restricted capacity between 5 KW – 200 KW pu. The main components of PLTMH Melong is Civil Buildings, Mechanical Components and Electrical Componentscomprising generator and control system, control system on PLTMH Melong there are two parts that musat be kept constant so that PLTMH always operate is voltage and frequency, controlled voltage can be set with AVR (Automatic Voltage Regulation) for the type of synchronous generator type STAMFORD, UCI 274E. If for frequency can be set with guide vane electro governor hydraulic. PLTMHcontrol system of setting the Active Power(P) produced at the output of the generator is need for Reactive Power (Q), Apparent Power (S) affecting the performance of the control system and compared to the ETAP programme 12.6.0
| Item Type: | Thesis (Diploma) |
|---|---|
| Uncontrolled Keywords: | Pembangkit Listrik Tenaga Mikro Hidro (PLTMH), Sistem Kontrol, ETAP 12.6.0 Micro-Hydro power plant (PLTMH), control system, ETAP 12.6.0 |
| Subjects: | Skripsi Bidang Keilmuan > Teknik Elektro |
| Divisions: | Fakultas Ketenagalistrikan dan Energi Terbarukan > S1 Teknik Elektro |
| Depositing User: | Sudarman |
| Date Deposited: | 26 Nov 2025 06:59 |
| Last Modified: | 26 Nov 2025 06:59 |
| URI: | https://repository.itpln.ac.id/id/eprint/4100 |