Hidayat, Muhammad Khairani and Hafidz, Mohammad (2017) ANALISIS KINERJA PLTS CIRATA 1 MW ON GRID. Diploma thesis, ITPLN.
SKRIPSI DAYAT.pdf
Restricted to Registered users only
Download (2MB)
Abstract
Pembangkit Listrik Tenaga Surya (PLTS) Cirata 1 MW di Purwakarta merupakan pembangkit listrik On Grid skala besar yang dibangun oleh PLN. PLTS Cirata menyuplai daya langsung ke jaringan PLN 20 kV dan ke jalur beban yang bersifat lokal. Sejak PLTS Cirata beroperasi oktober 2015, belum banyak diketahui potensi energi listrik yang optimum, hasil akhir/final yield (YF), dan performance ratio (PR) yang merupakan parameter-paremeter kinerja suatu PLTS. Sehingga perlu dilakukan analisis terkait kinerja PLTS Cirata dan kendala-kendala yang terjadi pada PLTS Cirata. Untuk mengetahui potensi optimum PLTS Cirata terkait dengan parameter kinerja maka dilakukan simulasi dengan menggunakan software PVSyst tanpa memperhatikan faktor shading yang kemudian hasil dari simulasi software dibandingkan dengan hasil produksi. Selisih produksi energi Pada Oktober-Maret 2017 selisih sebesar 16.64%, 5,2%, 34%, 5,2 %, 24%,10.4%. Performance ratio (PR) riil PLTS Cirata di Bulan Oktober 2016 - Maret 2017 berturut-turut adalah sebesar 79 %; 84 %; 59 %; 93%; 68% dan 79 %, rata-rata lebih rendah dibandingkan PR PLTS Cirata dari hasil simulasi di Bulan Oktober 2016 s/d Maret 2017 berturut-turut yaitu sebesar 89 %; 88,9 %; 89,4 %; 88,3%; 88,6% dan 88,6 %. Hasil kelayakan ekonomi, PLTS Cirata dikatakan layak karena setelah mencapai batas umur PLTS Cirata yaitu 25 tahun, modal awal atau investasi awal tertutup dengan BEP terjadi pada tahun ke 5 oleh kas masuk yang di dapat PLTS Cirata dengan Nilai NPV sebesar Rp 18.171.467.681
Solar power plant (PLTS) on Cirata 1 MW power plant in Purwakarta is On large scale Grid built by PLN. PLTS on Cirata supply power directly to the network and to kV PLN 20 lane loads that are local. Since the PLTS on Cirata operates October 2015, yet little-known potential for optimum electrical energy, final results/final yield (YF), and the performance ratio (PR) is a parameter-the performance an PLTS. So that needs to be done on Cirata PLTS performance related analysis and constraints that occur on the PLTS on Cirata. To find out the optimum potential on Cirata PLTS associated with performance parameters then done using simulation software PVSyst without regard to factors which then results from shading simulation software compared to the results of the production. The difference in energy production in the October-March 2017 difference amounted to 16.64%, 5.2%, 34%, 5.2%, 24%, 10.4%. Performance ratio (PR) real PLTS on Cirata in October 2016-March 2017 in a row is 79%; 84%; 59%; 93%; 68% and 79%, average lower than PR PLTS on Cirata from simulated results in October 2016 s/d March 2017 consecutive amounted to 89%; 88.9%; 89.4%; 88.3%; 88.6% 88.6%. The results of economic feasibility, PLTS on Cirata is said to be worth it because after reaching the age limit of the PLTS on Cirata of 25 years, the initial capital or initial investment with BEP occurs in 5 year by logging in can cash PLTS on Cirata value NPV of Rp 18.171.467.681
| Item Type: | Thesis (Diploma) |
|---|---|
| Uncontrolled Keywords: | PLTS Cirata, produksi energi listrik, hasil akhir harian (YF), performance ratio (PR), BEP PLTS Cirata, the production of electrical energy, final results daily (YF), the performance ratio (PR), BEP |
| Subjects: | Skripsi Bidang Keilmuan > Teknik Elektro |
| Divisions: | Fakultas Ketenagalistrikan dan Energi Terbarukan > S1 Teknik Elektro |
| Depositing User: | Sudarman |
| Date Deposited: | 26 Nov 2025 12:38 |
| Last Modified: | 26 Nov 2025 12:38 |
| URI: | https://repository.itpln.ac.id/id/eprint/4113 |