KONFIGURASI PENYULANG UNTUK MELAYANI PELANGGAN TM WTC MANGGA DUA DI PT. PLN (PERSERO) UP3 BANDENGAN

Tria, Chandrika Cahya Ratu and Pahiyanti, Novi Gusti (2019) KONFIGURASI PENYULANG UNTUK MELAYANI PELANGGAN TM WTC MANGGA DUA DI PT. PLN (PERSERO) UP3 BANDENGAN. Diploma thesis, ITPLN.

[thumbnail of BAB I-V.pdf] Text
BAB I-V.pdf
Restricted to Registered users only

Download (967kB)

Abstract

WTC Mangga Dua merupakan pelanggan Tegangan Menengah 20kV sebagai pusat server yang membutuhkan pasokan energi listrik yang besar untuk memenuhi kebutuhan listrik yang akan digunakan. Untuk mengetahui latar belakang kesesuaian konfigurasi jaringan pada WTC Mangga Dua yang terpasang dilakukan dengan perbandingan antara konfigurasi jaringan spindel dan konfigurasi jaringan spotload berdasarkan kuat hantar arus dari kabel yang digunakan. Dengan daya pelanggan sebesar 12.01 MVA dilakukan perhitungan beban untuk mencari kuat hantar arus dimana diperoleh hasil sebesar 434 Ampere. Batasan beban maksimal satu penyulang yakni sebesar 300 Ampere untuk kabel XLPE dengan luas penampang 3x240 mm2. Selain itu, dilakukan perhitungan perkiraan biaya untuk
konfigurasi jaringan spotload sekitar Rp 1,405,876,343.12 dan perkiraan biaya untuk konfigurasi jaringan spindel adalah sekitar Rp 1,028,194,245.08 Nilai ini diperoleh
berdasarkan asumsi perhitungan panjang segmen dengan harga satuan kabel yang digunakan.

WTC Mangga Dua is a 20 kV medium voltage customers as a central server which requires a large supply of electrical energy to meet the electricity needs to be used. To determine the suitability background network configuration on WTC Mangga Dua attached do with the ratio between the spindle network configuration and network configuration based on strong spotload of current-carrying wires used. With customers by 12:01 MVA power load calculation performed to look for where the current-carrying strong obtained yield was 434 Amperes. Limitation of the maximum load of the feeder which is equal to 300 Amperes for XLPE cable 3x240 mm2 cross sectional area. In addition, the calculation of cost estimates for the network configuration spotload around USD 1,405,876,343.12and the estimated cost for the network configuration spindle is approximately USD 1,028,194,245.08 This value is obtained by calculation assuming the segment length at a unit price of cable used.

Item Type: Thesis (Diploma)
Uncontrolled Keywords: Konfigurasi, spindle, spotload Configuration, spindle, spotload
Subjects: Skripsi
Bidang Keilmuan > Teknik Elektro
Divisions: Vokasi > D3 Teknologi Listrik
Depositing User: Sudarman
Date Deposited: 11 Feb 2026 07:28
Last Modified: 11 Feb 2026 07:28
URI: https://repository.itpln.ac.id/id/eprint/4982