KOORDINASI RELAI OCR PADA SISI INCOMING DAN SISI OUTGOING PENYULANG BODAK DI GI MANTANG

TARMIZI, KHAIRUL IMAM and Pahiyanti, Novi Gusti (2019) KOORDINASI RELAI OCR PADA SISI INCOMING DAN SISI OUTGOING PENYULANG BODAK DI GI MANTANG. Diploma thesis, ITPLN.

[thumbnail of cover dan pengesahan.pdf] Text
cover dan pengesahan.pdf

Download (850kB)
[thumbnail of BAB I,II,III,IV,V.pdf] Text
BAB I,II,III,IV,V.pdf
Restricted to Registered users only

Download (1MB)

Abstract

Dalam pendistribusian tenaga listrik sering kali terjadi gangguan. Ganggguan yang paling sering terjadi adalah gangguan hubung singkat dimana dalam mengatasi gangguan tersebut maka perlu dipasangnya relai arus lebih guna mengamankan peralatan listrik. Pemasangan relai arus lebih pada gardu induk harus terkoordinasi dengan baik antara relai satu dengan yang lainnya sehingga dapat mengurangi daerah padam listrik. Dalam penelitian ini membahas tentang sistem distribusi tenaga listrik, gangguan hubung singkat, sistem proteksi serta membahas tentang relai arus lebih beserta karakteristiknya. Metode yang digunakan pada penelitian ini menggunakan metode kuantitatif dimana pada metode ini menghitung besar impedansi sumber, reaktansi trafo dan impedansi saluran dimana total nilai impedansi tersebut digunakan untuk menghitung besar arus hubung singkat 2 fasa dan 3 fasa, dan hasil dari perhitungan arus hubung singkat tersebut digunakan untuk menentukan setting dari relai arus lebih pada gardu induk. Hasil dari perhitungan impedansi sumber, reaktansi trafo dan impedansi saluran didapat nilai total impedansi urutan positif dan negatifnya sebesar 8,4951+j11,5537, dan nilai arus hubung singkat 2 fasa dan 3 fasa sebesar 4573,8351A dan 5281,4098A. dari hasil tersebut maka didapat hasil setting relai arus lebih pada GI Mantang pada sisi outgoing penyulang Bodak sebesar 1,4751A dengan TMS 0,182 dengan waktu tunda 0,3 detik dan pada sisi incoming trafo 1 sebesar 0,9093A dan TMS 0,179 dengan waktu tunda 0,7 detik, sehingga dengan hasil demikian relai antara incoming dan outgoing sudah terkoordinasi dengan baik.

In the distribution of electric power interruption occurs frequently. The most common disturbance is a short circuit in overcoming the disorder where it is necessary the installation of the overcurrent relays in order to secure the electrical equipment. Installation overcurrent relays in substations must be well coordinated between the relay one another so as to reduce the area of electrical outages. In this study discusses the power distribution system, short circuit, the protection system as well as discuss the overcurrent relays and their characteristics. The method used in this study using a quantitative method whereby the large calculating the source impedance, reactance and impedance transformer through which the total value used to calculate the impedance of the large short-circuit current 2-phase and 3-phase, and the results of the short circuit current calculation used to determine the settings of overcurrent relays in substations. The results of the calculation of the source impedance, reactance and impedance transformer obtained channel total value of positive and negative sequence impedance of 8.4951 + j11,5537, and the value of short circuit current 2-phase and 3-phase for 4573,8351A and 5281,4098A. The results of the obtained results overcurrent relays setting on the GI Mantang the outgoing side of the feeder Bodak of 1,4751A with TMS .182 with a time delay of 0.3 seconds and on the incoming side of the transformer 1 of 0,9093A and TMS 0.179 with time delay 0, 7 seconds, so that with such results between incoming and outgoing relay has been coordinated.

Item Type: Thesis (Diploma)
Uncontrolled Keywords: Gangguan hubung singkat, Relai arus lebih, Setting relai, Koordinasi relai. Short circuit, overcurrent relays, relay settings, relay coordination.
Subjects: Skripsi
Bidang Keilmuan > Teknik Elektro
Divisions: Vokasi > D3 Teknologi Listrik
Depositing User: Sudarman
Date Deposited: 12 Feb 2026 07:38
Last Modified: 12 Feb 2026 07:38
URI: https://repository.itpln.ac.id/id/eprint/5008

Actions (login required)

View Item
View Item