KASTIO, WALI RAKA and Ridwan, Muhammad (2024) ANALISIS EFEKTIFITAS HIGH PRESSURE HEATER SEBELUM DAN SESUDAH PEMASANGAN PLUGGING TUBE UNIT 1 PT. PLN UBP OMBILIN. Diploma thesis, ITPLN.
![[thumbnail of TUGAS AKHIR_WALI RAKA KASTIO_202012051.pdf]](https://repository.itpln.ac.id/style/images/fileicons/text.png)
TUGAS AKHIR_WALI RAKA KASTIO_202012051.pdf
Restricted to Repository staff only
Download (5MB)
Abstract
Pembangkit Listrik Tenaga Uap (PLTU) merupakan komponen utama dalam infrastruktur energi global, terutama di wilayah yang kaya akan bahan bakar fosil. High Pressure Heater (HPH) di PLTU berfungsi untuk meningkatkan efisiensi termal dengan memanaskan air umpan sebelum masuk ke boiler. Di PLTU Ombilin, terjadi kebocoran pada tube HPH yang menyebabkan pemasangan plugging pada tube tersebut. Penelitian ini bertujuan untuk menganalisis pengaruh pemasangan plugging terhadap kinerja HPH serta faktor-faktor yang mempengaruhi efektifitas HPH. Sebelum pemasangan plugging, nilai Terminal Temperature Difference (TTD) tercatat sebesar 22,406°C, dengan Temperature Rise (TR) pada beban 50 MW dan 65 MW masing-masing sebesar 4622°C dan 4660°C. Setelah pemasangan plugging, terjadi peningkatan nilai TR menjadi 4919°C pada beban 50 MW dan 5158°C pada beban 65 MW, serta peningkatan Log Mean Temperature Difference (LMTD) di semua zona, yang menunjukkan penurunan efisiensi perpindahan panas. Hasil penelitian ini mengindikasikan bahwa meskipun plugging efektif dalam mengatasi kebocoran, pemasangannya berdampak negatif pada kinerja HPH secara keseluruhan. Disarankan untuk melakukan perbaikan menyeluruh pada HPH dan penelitian lebih lanjut mengenai efektifitas HPH guna meningkatkan efisiensi pembangkit listrik.
Steam Power Plants (PLTU) are key components of global energy infrastructure, particularly in regions rich in fossil fuels. The High Pressure Heater (HPH) in PLTUs serves to enhance thermal efficiency by preheating the feedwater before it enters the boiler. At the Ombilin PLTU, leaks occurred in the HPH tubes, leading to the installation of plugging on these tubes. This study aims to analyze the impact of plugging on HPH performance and the factors affecting HPH effectiveness. Before the plugging installation, the Terminal Temperature Difference (TTD) was recorded at 22.406°C, with a Temperature Rise (TR) of 4622°C at 50 MW and 4660°C at 65 MW. After plugging, the TR increased to 4919°C at 50 MW and 5158°C at 65 MW, along with an increase in the Log Mean Temperature Difference (LMTD) across all zones, indicating a decrease in heat transfer efficiency. The findings of this study suggest that while plugging is effective in addressing leaks, it negatively impacts overall HPH performance. It is recommended to carry out comprehensive repairs on the HPH and conduct further research on HPH effectiveness to improve power plant efficiency.
Item Type: | Thesis (Diploma) |
---|---|
Uncontrolled Keywords: | Steam Power Plant (PLTU), High Pressure Heater (HPH), thermal efficiency, plugging, Terminal Temperature Difference (TTD), Log Mean Temperature Difference (LMTD). PLTU, High Pressure Heater (HPH), Efisiensi termal, plugging, Terminal Temperature Difference (TTD), Log Mean Temperature Difference (LMTD). |
Subjects: | Skripsi Bidang Keilmuan > Teknik Mesin |
Divisions: | Fakultas Teknologi dan Bisnis Energi > S1 Teknik Mesin |