Kondensor adalah komponen vital dalam siklus termodinamika Pembangkit Listrik
Tenaga Gas Uap (PLTGU) yang berfungsi mengubah uap air bertekanan tinggi
menjadi cairan, sehingga efisiensi kondensor sangat menentukan kinerja
keseluruhan pembangkit listrik. Namun, seiring waktu, kondensor dapat mengalami
penurunan efektivitas akibat penumpukan kerak dan fouling, yang memerlukan
proses Overhaul untuk mengembalikan kinerja optimalnya. Penelitian ini
menganalisis efektivitas kondensor sebelum dan sesudah Overhaul di PLTGU
Cilegon, dengan metode komparatif yang melibatkan pengukuran kinerja
perpindahan panas pada beban 65 MW dan 100 MW. Hasil menunjukkan
peningkatan efektivitas kondensor dari 28,678% menjadi 32,673% pada beban 65
MW dan dari 32,429% menjadi 42,629% pada beban 100 MW setelah Overhaul,
yang dikaitkan dengan pengurangan fouling dan perbaikan laju aliran media
pendingin. Studi ini merekomendasikan penerapan program pemeliharaan rutin
untuk menjaga kinerja kondensor yang optimal dan memperpanjang umur
pakainya, serta menekankan pentingnya Overhaul dalam meningkatkan efisiensi
sistem pembangkitan di PLTGU.

The condenser is a vital component in the thermodynamic cycle of a Combined
Cycle Gas Turbine (CCGT) power plant, functioning to convert high-pressure
steam into liquid, thus making condenser efficiency crucial to the overall
performance of the power plant. However, over time, the condenser's effectiveness
can decline due to the buildup of scale and fouling, necessitating an Overhaul
process to restore optimal performance. This study analyzes the effectiveness of the
condenser before and after an Overhaul at the CCGT power plant in Cilegon, using
a comparative method that involves measuring heat transfer performance at 65 MW
and 100 MW loads. The results show a significant increase in condenser
effectiveness, from 28.678% to 32.673% at a 65 MW load and from 32.429% to
42.629% at a 100 MW load after the Overhaul, which is attributed to reduced
fouling and improved coolant flow rates. The study recommends the
implementation of routine maintenance programs to maintain optimal condenser
performance and extend its lifespan, while also emphasizing the importance of
Overhaul in enhancing the efficiency of power generation systems in CCGT plants.

Item Type: Thesis (Diploma)
Uncontrolled Keywords: Kondensor, PLTGU Cilegon, Overhaul, Efektivitas, Pemeliharaan, Fouling condenser, CCGT Cilegon, Overhaul, effectiveness, maintenance, fouling
Subjects: Skripsi
Bidang Keilmuan > Teknik Mesin
Divisions: Fakultas Teknologi dan Bisnis Energi > S1 Teknik Mesin
Depositing User: Nurul Hidayati
Date Deposited: 09 Sep 2025 08:04
Last Modified: 09 Sep 2025 08:04
URI: https://repository.itpln.ac.id/id/eprint/751

Actions (login required)

View Item
View Item